Breckenridge Material Co., et al., Respondents, v. Allied Home Corporation, et al., Appellants.

Decision date: Unknown

Slip Opinion Notice

This archive contains Missouri appellate slip opinions reproduced for research convenience, not the final official reporter version. Official source links remain authoritative where provided. Joseph Ott, Attorney 67889, Ott Law Firm - Constant Victory - Personal Injury and Litigation maintains these public legal archives to support Missouri case research and to help prospective clients connect that research to the firm's courtroom practice.

Opinion

This slip opinion is subject to revision and may not reflect the final opinion adopted by the Court. Opinion Missouri Court of Appeals Eastern District Case Style: Breckenridge Material Co., et al., Respondents, v. Allied Home Corporation, et al., Appellants. Case Number: No. 70838 Handdown Date: 09/02/1997 Appeal From: Circuit Court of St. Louis County, Hon. Herbert Laskey, Sr. Counsel for Appellant: Mark H. Zoole Counsel for Respondent: Donald E. Heck Opinion Summary: Two subcontractors brought an action in quantum meruit against Michael and Terry Murphy because the general contractor hired by the Murphys had failed to pay them. The court entered judgment in favor of the subcontractors. The Murphys appeal, claiming the verdict was not supported by substantial evidence. REVERSED AND REMANDED. DIVISION FIVE HOLDS: Since there was no evidence presented to prove that the Murphys had not paid the contract price for their home, they were not unjustly enriched; therefore, the subcontractors cannot recover under quantum meruit. Citation: Opinion Author: WILLIAM E. TURNAGE, Senior Judge Opinion Vote: REVERSED AND REMANDED. Ahrens, P.J., and Crandall, Jr., J., concur. Opinion:

Two subcontractors brought an action in quantum meruit against Michael and Terry Murphy because the general contractor hired by the Murphys had failed to pay them. The court entered judgment in favor of the subcontractors. The Murphys appeal, claiming the verdict was not supported by substantial evidence. Reversed. (FN1) In July of 1992, Michael and Terry Murphy contracted with Allied Home Corporation to construct a home

for them in Town and Country. The contract price was $231,195. Allied hired, among others, Tim Ortmann of Ortmann Stair Company to build a stairway and Panke Construction Services to do drywall work. In June of 1993, Allied abandoned the project. At that time Tim Ortmann was owed $2200 and Panke was owed about $5800. At trial, Ortmann and Panke introduced evidence of the work they had done and the fact that they had not been paid. The Murphys introduced evidence that they had paid a total of $259,529 for work and material that went into the house. The evidence of the Murphys that they had paid more than the contract price for labor and material for the house was uncontradicted. In Lee Bros. Contractors v. Christy Park Baptist Church, 706 S.W.2d 608 (Mo. App. 1986), this court examined the requirements for quantum meruit when an owner pays a general contractor but the general contractor fails to pay subcontractors. This court stated in Lee that "[q]uantum meruit is based primarily on the concept of unjust enrichment." Id. at 609. The court further stated that unjust enrichment occurs when retention of a benefit conferred without paying for it would be unjust. Id. The court further stated: Where the owner of the property has paid the contractor for the improvements there is nothing unjust about the owner's enrichment. Payment or nonpayment by the owner determines the most important element of a claim for quantum meruit--unjust enrichment. Non-payment by the owner must be pleaded and proved by the subcontractor in order to establish a cause of action for quantum meruit. Id. In International Paper Co. v. Futhey, 788 S.W.2d 303 (Mo. App. 1990), this court held: [W]here the landowner has paid a general contractor for the materials by paying the contract price, he is not unjustly enriched because he has paid for what he received. Even though the subcontractor remains unpaid and thus suffers detriment, equity will not require the owner to pay twice. Id. at 306. Thus the question in this case is not whether the subcontractors have been paid but whether or not the Murphys have paid the full contract price for the construction of their home.(FN2) In International Paper this court further stated: "The question of unjust enrichment focuses not upon what the contractor has received, but rather what the owner has paid." Id. The court also stated: Having paid the amount they were required to pay under the construction contract in the manner specified in that contract, the Sinklers were entitled to receive a completed residence in return. No unjust enrichment accrued to the Sinklers because Futhey defaulted forcing them to expend additional sums in order to obtain what they were entitled to under the contract. Id.

Ortmann and Panke contend that most of the money the Murphys were to pay for the construction of the home was placed in escrow and was paid out only on vouchers bearing the signature of Allied and one of the Murphys. After Allied withdrew, the Murphys signed both as contractor and owner. Ortmann and Panke contend that at the time Allied withdrew there was $11,000 in escrow from which they could have been paid. However, the evidence was uncontradicted that the Murphys paid in excess of $11,000 more for the home than the contract required. Under the above cases the court only inquires into the amount the owner has paid. The Murphys have paid more than the contract price. Thus, even though the subcontractors have not been paid, there can be no unjust enrichment because the law will not require the owner to pay twice. In this case there was no evidence to dispute the Murphys' evidence that they paid more than the contract price for labor and material furnished to construct their home. While it is unfortunate that the subcontractors in this case cannot recover, the law is clear that for them to recover under quantum meruit, they must prove that the Murphys have not paid the contract price for their home. Lacking that evidence, Ortmann and Panke have not proven their claim in quantum meruit. Since Ortmann and Panke failed to adduce evidence to establish their claim in quantum meruit, it follows that the judgment is not supported by substantial evidence and must be reversed. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). The judgment is reversed and this cause is remanded with directions to enter judgment in favor of the Murphys. Footnotes: FN1. The caption relates to other parties in the litigation who are not involved in this appeal. FN2. The same rule applies whether the owner pays the general contractor only, or pays part to the general and part to a sub-contractor. Northeast Painting v. AOC Int'l, 831 S.W.2d 711 (Mo. App. 1992). Separate Opinion: None This slip opinion is subject to revision and may not reflect the final opinion adopted by the Court.

Related Opinions

PAUL METZGER, and JACQUELINE METZGER, Respondents v. WAYNE MORELOCK, and KATHY MORELOCK, Appellants(2026)

Missouri Court of Appeals, Southern DistrictMarch 12, 2026#SD38930

affirmed

The trial court granted summary judgment to the Metzgers on their claim for a prescriptive easement over a portion of a paved driveway between their home and the Morelocks' property. The appellate court affirmed the grant of summary judgment, finding no genuine issue of material fact and that the moving party was entitled to judgment as a matter of law.

real-estateper_curiam1,904 words

Kevin Rosenbohm, Trustee of the Kevin and Michele Rosenbohm Family Trust Dated July 1, 2011 and Matt Rosenbohm and Nick Rosenbohm vs. Gregory Stiens, and Gregory Stiens, Trustee of the Anthony Stiens Trust(2026)

Missouri Court of Appeals, Western DistrictMarch 3, 2026#WD87720

affirmed

The court affirmed the circuit court's judgment in favor of the Rosenbohms on their adverse possession and trespass claims against Stiens regarding disputed tracts of property in Nodaway County. The court rejected Stiens's arguments regarding excluded evidence, cross-examination, jury instructions on permissive use defense, and remanded the case for the court to amend the judgment with precise legal descriptions of the disputed property.

real-estatemajority3,613 words

Arthur F. Daume, Jr., and Gayle C. Daume, Appellants, v. Thomas Szepanksi, et al., Respondents.(2026)

Missouri Court of Appeals, Eastern DistrictFebruary 3, 2026#ED113073

reversed

In this quiet title appeal, the court reversed the trial court's interpretation of an easement deed that the Daumes held over a private roadway. The court rejected the trial court's constructions that the easement's 'non-commercial purposes' limitation prohibited agricultural use and that it was restricted to the Daumes and their immediate family members.

real-estatemajority2,252 words

Colleen Eikmeier and William S. Love, Appellants, vs. Granite Springs Home Owners Association, Inc. A Missouri Not-For-Profit Corp., Respondent.(2026)

Supreme Court of MissouriJanuary 23, 2026#SC101161

reversed

The Missouri Supreme Court reversed the circuit court's judgment and held that a 2022 statute prohibiting homeowners' associations from banning solar panel installations applies to preexisting covenants, not just prospective ones. The homeowners' challenge to the HOA's restriction on solar panels visible from the street was successful, as the statute's prohibitions supersede prior restrictive covenants.

real-estatemajority4,531 words

State of Missouri, ex rel., State Tax Commission vs. County Executive of Jackson County, Missouri, Assessor of Jackson County, Missouri, Jackson County Board of Equalization, through its Members in their Official Capacities, Clerk of the Jackson County, Missouri, Legislature(2025)

Missouri Court of Appeals, Western DistrictDecember 30, 2025#WD87831

affirmed
real-estatemajority3,220 words